Road Renewal July Construction Schedule

Please note: these dates are tentative and weather dependent.

Concrete sidewalk replacement
Expect traffic disruptions and temporary closures to accommodate concrete work at the following locations June 30th – July 31st:

  • 80 Ave (114 – 119 St)
  • University Ave service road (114 – Saskatchewan Drive)
  • East side 119 Street (76 Ave – University Ave)
  • 77 Ave (118 – 115 St)
  • 75 Ave (114 – 118 St)
  • 74 Ave (118 – 116 St) (After June 28th)
  • 76 Ave Sidewalk construction. Saskatchewan Drive – 114 Street (Approx. start July 9th)
  • 78 Ave (119 – 115 St)
  • 79 Ave (119 St – 78 Ave)

Road re-construction/Reclamation

  • July 15 – Expect staged closures for road reconstruction/reclamation in the following areas South of 76 Ave to 74 Ave.
  • Saskatchewan Drive to 114 Street; between 76 Ave and 74 Ave (incl. 74 Ave). Residents can expect bulletins prior to long term roadway closures (More than 1 day).

Paving

  • Saskatchewan Drive; West shared use pathway paving (tentatively scheduled for June 29-30th)
  • Paving to follow roadway base construction: Saskatchewan Drive to 114 Street; Between 76 Ave and 74 Ave (incl. 74 Ave).