Belgravia Square Update December 13 2018

Steel erection is almost complete. Drilling wells for the geothermal heating and cooling system is in progress. Precast concrete floor installation is in progress. Concrete pouring over the precast f...

Belgravia Square Update November 1 2018

Pile driving on the site has been completed. Steel and concrete work are underway. There will be an increase in large truck traffic delivering supplies to the site. On occasion the developer will nee...

Construction begins at Keillor Point

Construction of Keillor Point (formerly referred to as “The End of the World”) has started today – October 22, 2018. Over the next few months, the exposed concrete piles will be cut off and a n...

Belgravia Square Update September 18th 2018

Wet weather conditions have delayed completion of the pile driving. The site needs to dry out before it can continue. Water will be pumped from the site this week. There are about four days of pile d...

Road Renewal Update September 2018

Park Paving are drawing nearer to the end of work in the Belgravia neighbourhood with September and October being the busiest months in the project as they progress through road re-constructions. Par...